Important Math Questions for AFCAT Exams \\ MATHS\\
IMPORTANT MATHS QUESTION FOR AFCAT
Q.1 A can finish a work in 18 days
and B can do the same work in half the time taken by A. then, working together,
what part of the same work they can finish in a day?
(a) 1/6 (b) 1/9 (c) 2/5 (d) 2/7
Q.2 A, B and C can complete a piece
of work in 24, 6 and 12 days respectively. Working together, they will complete
the same work in:
(a) 1/24 day (b) 7/24 day (c) 24/7 day (d) 4 days
Q.3 A man can do a piece of work in
5 days, but with the help of his son, he can do it in 3 days. In what time can
the son do it alone?
(a) 13/2 days (b) 7 days (c)
15/2 days (d) 8 days
Q.4 A can lay railway track between
two stations in 16 days and B can do the same job in 12 days. With the help of
C, they did the job in 4 days only. Then, C alone can do the job in:
(a) 46/5 days (b) 47/5 days (c)
48/5 days (d) 10 days
Q.5 A takes twice as much as B or
thrice as much time as C to finish a piece of work. Working together, they can
finish the work in 2 days. B can do the work alone in:
(a) 4 days (b) 6 days (c) 8 days (d) 12 days
Q.6 A and B are working on an assignment.
A takes 6 hours to type 32 pages on a computer, while B takes 5 hours to type
40 pages. How much time will they take, working together on two different
computers to type an assignment of 110 pages?
(a) 7 hours 30 min. (b) 8 hours (c)
8 hours 15 min. (d) 8 hours 25 min.
Q.7 A and B can do a work in 8 days, B
and C in 12 days. A, B and C work together can finish it in 6 days. A and C
together will do it in:
(a) 4 days (b) 6 days (c) 8 days (d) 12 days
Q.8 A works twice as fast as B. If B can
complete a work a work in 12 days independently, the number of days in which A
and B can together finish the work is:
(a) 4 days (b) 6 days (c) 8 days (d) 18 days
Q.9 A is thrice as good a workman
as B and therefore is able to finish a job in 60 days less than B. working
together, they can do it in:
(a) 20 days (b) 45/2 days (c) 25 days (d) 30 days
Q.10 Amit can do a piece of work in
20 days. Pankaj is 25 % more efficient than Amit. The number of days taken by
Pankaj to do the same piece of work is:
(a) 15 days (b) 16 days (c) 18 days (d) 25 days